Kt Kingtronics File Global Lead Time Information in Electronics Industry

ACTIVES
Technology Manufacturer Current 

Lead-Times

Lead-Times

Trend

Comments
Rectifiers Diodes Inc 12-24 Increasing Schottky rectifiers SOT23 and SOD323 20- 24 weeks, PDI123 21 weeks, SBR TO220AB 12-20 weeks, SMA 16-18 weeks.
Vishay 16-52 Increasing There are increased lead times in SMA, SMB, SMC, TO-220, TO-263 and DPAK. Schottkys are most affected with 40-52 weeks lead time.
ON Semiconductor 18-42 Increasing SOD123 flat lead, SOT23 copper and SMA Flat lead 36-42 weeks lead time. Automotive parts 26-32 weeks
STMicroelectronics 20-33 Increasing TURBO 2 Ultrafast High Voltage Rectifiers running about 20 weeks. Everything else is 25-33 weeks.
Fairchild 12-14 Stable
TVS Diodes Diodes Inc 12-16 Increasing
Littelfuse 16 Increasing Purchased ON Semi TVS business Lead times 24 weeks
Vishay 25-40 Increasing SMC at 25 weeks SMA and SMB at 40
STMicroelectronics 8 Stable
Schottky Diodes Diodes Inc 12-22 Increasing
Nexperia 20-40 Increasing SOT23SD/DD from 20 to 45 weeks – SOD523 from 40 weeks – – SOT 89 40 WEEKS – SOT323SD/DD from 40 weeks SOT363 from 30 to 40 weeks SOT353P 20-40 WEEKS SOD123F 30 WEEKS DHVQFN14/16/20/24 from 12 to 24 weeks – DFN PACKAGES 20 weeks – SOD 323 26 WEEKS – SOT 223 40 WEEKS – DSN PACKAFES 20 WEEKS
ON Semiconductor 20-40 Increasing SMA 23-40 WEEKS – SMB 23-40 WEEKS – SMC 28-33 WEEKS – SOT 23 COPPER 20-45 WEEKS – SOT 89 16-30 WEEKS – SOT223 40 WEEKS – TO220 16-22 WEEKS – SOD 923 18-22 WEEKS – SOIC-8-14-16 20-30 WEEKS – SOD123 COPPER 20-30 WEEKS – SOD 323 DPAK 20-30 WEEKS – DFN PACK 20-52 WEEKS – SC 70 18-30 WEEKS
Fairchild 16-45 Increasing
Switching Diodes Diodes Inc 12-22 Increasing
Fairchild 16-45 Increasing
ON Semiconductor 16-40 Increasing SMA 23-40 WEEKS – SMB 23-40 WEEKS – SMC 28-33 WEEKS – SOT 23 COPPER 20-45 WEEKS – SOT 89 16-30 WEEKS – SOT223 40 WEEKS – TO220 16-22 WEEKS – SOD 923 18-22 WEEKS – SOIC-8-14-16 20-30 WEEKS – SOD123 COPPER 20-30 WEEKS – SOD 323 DPAK 20-30 WEEKS – DFN PACK 20-52 WEEKS – SC 70 18-30 WEEKS
Nexperia 20-40 Increasing SOT23SD/DD from 20 to 45 weeks – SOD523 from 40 weeks – – SOT 89 40 WEEKS – SOT323SD/DD from 40 weeks SOT363 from 30 to 40 weeks SOT353P 20-40 WEEKS SOD123F 30 WEEKS DHVQFN14/16/20/24 from 12 to 24 weeks – DFN PACKAGES 20 weeks – SOD 323 26 WEEKS – SOT 223 40 WEEKS – DSN PACKAFES 20 WEEKS
Zener Diodes Diodes Inc 12-22 Increasing
Fairchild 10-30 Increasing
Nexperia 6-40 Increasing SOT23SD/DD from 20 to 45 weeks – SOD523 from 40 weeks – – SOT 89 40 WEEKS – SOT323SD/DD from 40 weeks SOT363 from 30 to 40 weeks SOT353P 20-40 WEEKS SOD123F 30 WEEKS DHVQFN14/16/20/24 from 12 to 24 weeks – DFN PACKAGES 20 weeks – SOD 323 26 WEEKS – SOT 223 40 WEEKS – DSN PACKAFES 20 WEEKS
ON Semiconductor 12-40 Increasing SMA 23-40 WEEKS – SMB 23-40 WEEKS – SMC 28-33 WEEKS – SOT 23 COPPER 20-45 WEEKS – SOT 89 16-30 WEEKS – SOT223 40 WEEKS – TO220 16-22 WEEKS – SOD 923 18-22 WEEKS – SOIC-8-14-16 20-30 WEEKS – SOD123 COPPER 20-30 WEEKS – SOD 323 DPAK 20-30 WEEKS – DFN PACK 20-52 WEEKS – SC 70 18-30 WEEKS
Vishay 12-44 Increasing SMA SMB – 28-44 WEEKS
Bridge Rectifiers Diodes Inc 16-30 Increasing DFxx series 25-30 weeks, KBPxx series 21-25 weeks.
Fairchild 12-42 Increasing
Vishay 19-45 Increasing
General Purpose Transistors Diodes Inc 12-22 Increasing
Fairchild 10-40 Increasing
Nexperia 13-40 Increasing SOT23SD/DD from 20 to 45 weeks – SOD523 from 40 weeks – – SOT 89 40 WEEKS – SOT323SD/DD from 40 weeks SOT363 from 30 to 40 weeks SOT353P 20-40 WEEKS SOD123F 30 WEEKS DHVQFN14/16/20/24 from 12 to 24 weeks – DFN PACKAGES 20 weeks – SOD 323 26 WEEKS – SOT 223 40 WEEKS – DSN PACKAFES 20 WEEKS
ON Semiconductor 12-40 Increasing SMA 23-40 WEEKS – SMB 23-40 WEEKS – SMC 28-33 WEEKS – SOT 23 COPPER 20-45 WEEKS – SOT 89 16-30 WEEKS – SOT223 40 WEEKS – TO220 16-22 WEEKS – SOD 923 18-22 WEEKS – SOIC-8-14-16 20-30 WEEKS – SOD123 COPPER 20-30 WEEKS – SOD 323 DPAK 20-30 WEEKS – DFN PACK 20-52 WEEKS – SC 70 18-30 WEEKS
Rohm Semiconductor 10-60 Increasing The following packages have been extended to 40 weeks CPT – TSMT356 – TSMT36M – TSMT8 – TSMT8M – SOP8 – UMD2M – USM – EMD2M – EMD2 – TUSH/TUMD2S – PMDU – PMDUM – PSM – PMDS – SSOP5 – SSOP6
PASSIVES
Trimmers & Pots BI Tech 8-12 Stable
Piher 10-14 Stable
Panasonic 14-16 Decreasing Pots will be EOL by the end of 2017
Vishay 10-14 Stable
Electrolytic NIC Components 18-20 Increasing Leadtimes pushed out. Some pricing has been increased. Pushouts some cases 40 weeks
Nichion 18-28 Stable SMD 10×10,8×10,6.3×7.7 Leadtimes coming down now between 18-24, Snap-in still 28-30, price increases happening
Surge 14-19 Increasing Lead-times pushing out closing on 20 weeks on some products
Panasonic 14-18 Decreasing Some SMD dropping from 18 to 16 weeks. Some price increases.
United Chemicon 16-20 Increasing Leadtimes increasing the 18-20 weeks
Capacitors – Tantalum AVX 20-28 Increasing Long lead-times across all case sizes
Vishay 15-20 Increasing Lead-times extending on small case sizes A & B
Leaded Capacitors – Ceramic AVX 18-20 Stable
Murata 18-20 Stable A lot of parts EOL’d
Vishay 12-16 Stable
NIC Components 14-18 Increasing
TDK 14-20 Increasing
Surface Mount General Capacitors – Ceramic AVX 24+ Increasing Automotive Specs Sold Out, Allocation on 44 series of parts. Controlled order entry on long list of parts
Murata 20-38+ Increasing Controlled order entry on a long list of parts, mostly large case sizes. EOL notification on many parts
Samsung 24+ Increasing Lead times under pressure, price increases in Q1 2018
TDK 24+ Increasing On severe allocation
Taiyo Yuden 30+ Increasing On severe allocation
NIC Components 24+ Increasing
Yageo 38+ Increasing Price increase in Q1 2018, Controlled order entry on long list of parts
Walsin 40+ Increasing
Vishay 16+ Stable

Kt-File-Global-Lead-Time-Information

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s